Efforts to bury all utility wires in SF nearly impossible
"""
Utility customers pay about a dollar a month [for the last 50 years] for a program that is supposed to bury all those wires. At the current rate of replacement, [...] It will take 600 years. [...] San Francisco has already put roughly half of its utility lines underground, [...] the city has no plan to bury the remaining wires because it has already spent the money.

The last time the city buried any wires was on project on Octavia Boulevard in 2005. It ran so far over budget the city used up all the money that will be coming in for the next 15 years.
"""
http://abc7news.com/news/efforts-to-bury-all-utility-wires-in-sf-nearly-impossible-/486804/
http://abc7news.com/news/efforts-to-bury-all-utility-wires-in-sf-nearly-impossible-/486804/